If we are to model the Nigerian 330kV transmission line between Kainji hydro power sub-station in Niger state and New-heaven sub-station in Enugu state, which model would you suggest? Justify your answer.
Provide your response in the comment section using your surname and last two digit of your matriculation number as your identity (e.g. Abacus20)
Click here to like and follow the E-Learning Community on Facebook for more interactive practices and discussions with peers and instructor.
Feel free to tag your engineering friends and hashtag other social networks and learning websites.
Adegun03
ReplyDeleteLong line transmission model is suitable. This is because distance from Enugu to Niger is about 470Km or more, and according to what we've been taught, long line transmission is within the range of 240km and above.
Good one!!👍👍⚙️🔌💡
DeleteLong line model is wat we can use to model the transmission line from kainji(Niger) to new heaven sub station in Enugu.This is because the distance is roughly 475km and the transmission line is 330kv;An overhead transmission line has a distance above 250 km and line voltage above 100kv.OTUNNI 11
ReplyDeleteYou are recognized!!!
DeleteAlways Consistent with responses 👍👍
The Long line transmission model is the most suitable sir. The distance from Enugu to Niger is about 470Km, and as we were told in class, long line transmission is within the range of 240km and above.
ReplyDelete👍👍⚙️
DeleteLong Line Transmission Line is preferred because of the far distance between the two power plants
ReplyDeleteHow far is the far distance?
DeletePlease always be precise with your answers.
Long line is above 150km
DeleteThe distance between Kainji hydro power sub-station in Niger state and New-heaven sub-station in Enugu state is estimated to be 475km, so therefore Long line Transmission model is employed.
ReplyDeleteOf course its a long line. But your answer is yet to be justified.
DeleteA long transmission line is defined as a transmission line with an effective length more than 250 km (150 miles)
ReplyDeleteAnd the approximated distance between Kainji hydro power sub-station in Niger state and New-heaven sub-station in Enugu state is about 475km with a transmission line of 330kV.
Therefore, a long line model is more suitable for the modelling of the transmission line.
Long transmission line modelling will be suitable, since the distance between kainji power substation in Naija state and New heaven power substation Enugu state is more 150km and the voltage is more a 100kv which is the standard for a long transmission model to be used, it is there by justified using a long transmission line model
DeleteSaheed56, Long line model is wat we can use to model the transmission line from kainji(Niger) to new heaven sub station in Enugu.This is because the distance is roughly 475km and the transmission line is 330kv;An overhead transmission line has a distance above 250 km and line voltage above 100kv.
ReplyDelete👍👍
Delete
ReplyDeleteGbadebo 32, Long transmission line model will be suitable, since the distance between kainji power substation in Naija state and New heaven power substation Enugu state is more than 150km and the voltage is more a 100kv which is the standard for a long transmission model to be used, it is there by justified.
👍👍
DeleteLong line transmission model may be the best suitable. This is because distance from Niger to enugu is about 472 Km or more, and according to what we've been told in class, long line transmission is within the range of 240km and above.
ReplyDelete👍👍⚙️
DeleteThe distance between Niger and Enugu is approximately 455.5km which is greater than 150km and the voltage to be transmitted is High 330kv greater than 100kv been the standard rating long transmission. Therefore, Long transmission line modelling will suitable for the purpose.
ReplyDeleteLong Transmission line modelling is the best option since,the distance from Niger to Enugu is 455.5km and the voltage to be transmitted is 330km. Whereas the standard rating for long transmission is >240km and >100kv
ReplyDeleteLong transmission line modelling is required because its 330kv line to line voltage and the estimated distance between Niger state and Enugu is over 450km,every long transmission line must have a distance above 250km
ReplyDeleteLong line transmission model will be suitable because of the distance between Niger and Enugu is 455.5km which is much more greater than 150km and the voltage to be transmitted is high "330kv" greater than "100kv" been the standard rating long transmission.
ReplyDeleteThe distance between Kainji hydro power sub-station in Niger state and Enugu state is estimated to be 475km... Long line transmission model is the best suitable according to what we've been told in class, long line transmission is within the range of 240km and above.
ReplyDeleteLong line model is wat we can use to model the transmission line from kainji(Niger) to new heaven sub station in Enugu.This is because the distance is roughly 475km and the transmission line is 330kv;An overhead transmission line has a distance above 250 km and line voltage above 100kv.OTUNNI 11
ReplyDeleteREPLY
http://astoldpost.blogspot.com/....you are valid❤❤❤
Long Transmission line modelling will be preferable because the distance from Niger to Enugu is 455.5km and the voltage to be transmitted is 330km. And the standard rating for long transmission is >240km and >100kv
ReplyDeleteLong line model will be used to model the transmission line from kainji(Niger state) to new heaven sub station in Enugu. because thir distance apart is roughly 475km and the transmission line is 330kv;An overhead transmission line has a distance above 250 km and line voltage above 100 killo~volt
ReplyDeleteThe Long line transmission model is the most suitable. The distance from Enugu to Niger is about 470Km, and we were told in class, long line transmission is within the range of 240km and above.
ReplyDeleteFor 330kv a distance of 475km is required, hence the transmission suitable for such is long transmission.
ReplyDeleteThe distance covered for 330kv is 475km and for such long transmission line is required.